Search results for: Cameron LNG

86520 results

A list of search results

  • 10 July 2014

    The U.S. Department of Energy (DOE) approved changes in control of Cameron LNG’s FTA authorization, and its conditional non-FTA authorization. On February 18, 2014, Cameron LNG, a unit of Sempra, filed an application with the Office of Fossil Energy (FE) of the DOE to transfer indirect control of two DOE/FE export authorizations that it currently holds. These […]

  • 13 October 2015

    Sempra Energy’s Cameron LNG is moving forward with the construction of its liquefaction and export project in Hackberry, Louisiana. “In just over a year Cameron LNG has cleared the ground for the liquefaction project and over 800 team members are working on site in two shifts,” the company said in its latest project update. The project […]

  • 14 May 2019

    Sempra Energy said that production of liquefied natural gas (LNG) from the first liquefaction train started at the Cameron LNG export project in Hackberry, Louisiana. 

  • 25 December 2019
    Business & Finance

    Cameron LNG has begun producing LNG from the second liquefaction train of the export facility in Hackberry.

  • 16 April 2019

    Sempra Energy said that Cameron LNG started feeding pipeline gas to the first liquefaction train of the LNG export project as it prepares to start production at the facility in Hackberry, Louisiana.

  • 22 April 2020
    Authorities & Government, Business developments & projects, Project & Tenders, Regulation & policy

    The United States energy regulators granted Sempra-led Cameron LNG to start the commissioning process of the third liquefaction train at its export plant in Louisiana. The Federal Energy Regulatory Commission said in an order dated April 21 it allows Cameron LNG to introduce “hazardous fluids and commission the Train 3 feed gas to warm end […]

  • 16 April 2015

    The US Department of Energy issued an order granting long-term, multi-contract authorization to export LNG to free trade agreement countries to Cameron LNG, from it’s terminal in Camron Parish, Louisiana.

  • 23 April 2020
    Business developments & projects, Project & Tenders

    The Sempra Energy-led Cameron LNG project has started commissioning the third liquefaction train at its export plant in Louisiana. Cameron LNG began introducing feed gas to the third train on Wednesday, according to a Sempra statement. This also marks the final commissioning stage for the first phase of the LNG export facility worth about $10 […]

  • 8 May 2015

    Cameron LNG said it will hold two open house meetings to provide information to the community about the plans to further expand the liquefaction facility currently under construction at the site of the Cameron LNG terminal near Hackberry.

  • 15 May 2019
    Business & Finance

    LNG exports to international markets expected to commence in the coming weeks.

  • 8 May 2015

    Cameron LNG said it will hold two open house meetings to provide information to the community about the plans to further expand the liquefaction facility currently under construction at the site of the Cameron LNG terminal near Hackberry.

  • 23 July 2019

    Sempra Energy’s Cameron LNG export project has requested the Federal Energy Regulatory Commission authorization to place the first liquefaction train in service. 

  • 28 January 2020

    Cameron LNG project has filed a request with the Federal Energy Regulatory Commission seeking a 72-month extension to place additional facilities in service. 

  • 3 March 2020
    Ports & Logistics

    Sempra LNG, a unit of Sempra Energy, said that the second liquefaction train at the Cameron LNG project in Hackberry, Louisiana, has begun commercial operations under its tolling agreements.

  • 16 April 2015

    The US Department of Energy issued an order granting long-term, multi-contract authorization to export LNG to free trade agreement countries to Cameron LNG, from it’s terminal in Camron Parish, Louisiana.

  • 23 December 2019

    Sempra LNG, a unit of Sempra Energy, informed that Cameron LNG has begun producing liquefied natural gas (LNG) from the second liquefaction train of the export facility in Hackberry, Louisiana.  

  • 23 May 2019

    LNG contractor McDermott International said the production from the final train of the Cameron LNG project in Hackberry, Louisiana, is set to start production in the second quarter of 2020. 

  • 14 July 2015

    The United States Department of Energy issued an order granting a long-term, multi-contract authorization to export liquefied natural gas to Cameron LNG equivalent to approximately 515 billion cubic feet per year to free trade agreement countries.

  • 30 May 2019
    Vessels

    Sempra Energy started loading the first cargo of the chilled fuel at its Cameron LNG export project in Hackberry, Louisiana. 

  • 14 July 2015

    The United States Department of Energy issued an order granting a long-term, multi-contract authorization to export liquefied natural gas to Cameron LNG equivalent to approximately 515 billion cubic feet per year to free trade agreement countries.

  • 3 May 2012
    Project & Tenders

      Sempra Energy subsidiary Cameron LNG today announced it has signed a third and final commercial development agreement with a subsidiary of GDF SUEZ to develop the remaining liquefaction train planned at the site of the Cameron LNG terminal in Hackberry, La. With this agreement of 4 million tonnes per annum (Mtpa) with GDF SUEZ, […]

  • 6 March 2015

    The construction of Cameron LNG’s liquefaction facilities that kicked off in October, 2014, has been progressing.