Search results for: trianel-windpark-borkum-ii

43833 results

A list of search results

  • 15 October 2019
    Operations & Maintenance

    Deutsche Windtechnik has received an order to provide maintenance for the 32 Senvion 6.3M 152 turbines at the Trianel Windpark Borkum II wind farm in the German North Sea. The main service tasks include troubleshooting the wind turbines, including guaranteed availability, remote fault elimination, spare parts management, and logistics from Borkum or Emden. “We are […]

  • 5 December 2019

    The Trianel Windpark Borkum II (TWBII) offshore wind project has reached the halfway turbine installation point as 16 out of 32 units have been erected. Jan De Nul’s jack-up vessel Taillevent installed the 16 Senvion 6.2M152 turbines in the northeastern part of the project site offshore Germany, with the installation of the remaining 16 units […]

  • 5 December 2019

    The Trianel Windpark Borkum II (TWBII) offshore wind project has reached the halfway turbine installation point as 16 out of 32 units have been erected. Jan De Nul’s jack-up vessel Taillevent installed the 16 Senvion 6.2M152 turbines in the northeastern part of the project site offshore Germany, with the installation of the remaining 16 units […]

  • 9 November 2018

    27 out of the 32 monopile foundations have been installed on the 200MW Trianel Windpark Borkum II (TWB II) offshore wind farm in the German North Sea.

  • 13 June 2017
    Equipment, Project & Tenders

    Sif Holding has secured, in a joint venture with Smulders, the production of all monopiles and transition pieces for the Trianel Windpark Borkum II wind farm project. The JV was awarded the contract by EPCI-contractor Seaway Heavy Lifting. Sif will produce the monopiles and transition pieces in joint venture with Smulders, together comprising approximately 32 Ktons, during […]

  • 5 September 2018

    Seaway Heavy Lifting’s (SHL) vessel Stanislav Yudin has installed 16 out of 32 monopile foundations at the Trianel Windpark Borkum II in the German North Sea.

  • 24 July 2019

    Jan De Nul’s offshore installation vessel Taillevent has begun loading the first turbine components for the Trianel Windpark Borkum II (TWBII) offshore wind farm. The 200MW TWBII offshore wind farm will comprise 32 Senvion 6.2M152 turbines installed at the project site some 40km north of the island of Borkum in Germany. Taillevent loaded the first three towers, blades […]

  • 15 November 2018
    Ports & Logistics

    The Buss Terminal Eemshaven has received the first shipment of wind turbine tower sections for the Trianel Windpark Borkum II offshore wind project.

  • 14 May 2020
    Project & Tenders

    The Blue Tern installation vessel is currently at the Trianel Windpark Borkum II (TWBII) project site with the last two turbines to be installed. Our sister news site OffshoreWIND.biz contacted Fred. Olsen Windcarrier after Buss Energy Group, which has been providing port logistics for wind turbine installation, reported it had completed its project for Trianel […]

  • 18 May 2020
    Project & Tenders

    The 32nd and final wind turbine at the Trianel Windpark Borkum II (TWBII) site was installed on Sunday, 17 May. “The last big components were installed Saturday, and final bolt and nut Sunday early morning”, Fred. Olsen Windcarrier informed on 18 May. Fred. Olsen Windcarrier was contracted in February to install eleven turbines on the […]

  • 7 August 2018
    Ports & Logistics, Project & Tenders

    Trianel Windkraftwerk Borkum II GmbH has issued a tender for the provision of a guard vessel during the construction of the Trianel Windpark Borkum II wind farm in the German North Sea.

  • 29 June 2018
    Storage

    Jan De Nul has completed the export cable installation works at the Trianel Windpark Borkum II and the Borkum Riffgrund 2 offshore wind farms in the German North Sea.

  • 28 February 2018
    Project & Tenders

    Senvion has contracted TÜV Rheinland to oversee the production of wind turbine blades for the Trianel Windpark Borkum II offshore wind farm.

  • 1 June 2017
    Storage

    Jan De Nul has contracted Seaproof Solutions to supply its export cable protection systems (CPS) for the Borkum Riffgrund 2 offshore wind farm and Trianel Windpark Borkum II.

  • 25 November 2016
    Business & Finance, Operations & Maintenance, Project & Tenders

    Seaway Heavy Lifting has been awarded a contract for engineering, procurement, construction and installation (EPCI) of the turbine foundations for the Trianel Windpark Borkum II wind farm on the German continental shelf. According to the company, the award is still subject to financial close of the full project which is expected in the first half of […]

  • 31 July 2018

    Eight out of 32 monopile foundations have been installed on the Trianel Windpark Borkum II in the German North Sea, the project’s developers said.

  • 28 February 2018
    Project & Tenders

    Senvion has contracted TÜV Rheinland to oversee the production of wind turbine blades for the Trianel Windpark Borkum II offshore wind farm.

  • 28 March 2019
    Ports & Logistics

    The first wind turbine nacelles built by Senvion for the Trianel Windpark Borkum II wind farm have started their journey to the Buss Terminal Eemshaven in the Netherlands. The first of the 32 Senvion 6.2M152 wind turbines are expected to be installed at the site some 40 kilometres north of the island of Borkum in the German North Sea […]

  • 2 August 2019

    Jan De Nul’s jack-up Taillevent has started installing the first wind turbine on the 200MW Trianel Windpark Borkum II (TWBII) wind farm offshore Germany. Taillevent loaded the first three sets of turbine components at Buss Terminal Eemshaven prior to transporting them to the site some 40 kilometres north of the island of Borkum in the German North Sea. […]

  • 30 November 2018

    EMS Maritime Offshore GmbH (EMO) deployed one of its specialist vessels at the Trianel Windpark Borkum II (TWB II) offshore wind farm site in early November 2018 to secure the shipping traffic during construction. 

  • 14 November 2019

    13 of the 32 Senvion 6.2M152 wind turbines have been installed on the 200MW Trianel Windpark Borkum II (TWBII) offshore wind farm in the German North Sea, Trianel GmbH said. Eleven out of the thirteen turbines installed have been commissioned, according to Trianel. The wind turbines are being loaded by Jan De Nul’s jack-up Taillevent at Buss […]

  • 15 August 2019

    Jan De Nul’s vessel Taillevent has installed the first turbine at the Trianel Windpark Borkum II (TWBII) offshore wind farm. The 200MW TWBII wind farm will comprise 32 Senvion 6.2M152 turbines installed on monopile foundations at the site some 40km north of the island of Borkum in the German North Sea. Taillevent is loading the turbine components in sets […]