Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Premier Orders Two Wellhead Platforms (Indonesia)
Fossil Energy

June 4, 2012 · about 14 years ago

Premier Orders Two Wellhead Platforms (Indonesia)

Sembcorp Marine‘s subsidiaray SMOE Pte Ltd has secured a contract worth about US$175 million from Premier Oil Natuna Sea B.V. for the engineering and construction of 2 Wellhead Platforms, 2 infield sub-sea pipelines and modification works on an existing facility for the Naga and Pelikan Project, off

1 minutes read
  • LinkedIn
  • X
  • Email

Sembcorp Marine ‘s subsidiaray SMOE Pte Ltd has secured a contract worth about US$175 million from Premier Oil Natuna Sea B.V. for the engineering and construction of 2 Wellhead Platforms, 2 infield sub-sea pipelines and modification works on an existing facility for the Naga and Pelikan Project, offshore Indonesia.

The platform topside and jacket each weighs approximately 480 and 900 metric tonnes respectively. The sub-sea pipelines of 14 inch diameter by 19 km and 12 inch diameter by 32 km are tied to the existing Central Processing Platform.

PT SMOE Indonesia’s scope of work, worth about US$63 million, entails engineering design, procurement, construction, offshore hook-up and commissioning of the 2 platforms and modification work on the existing Central Processing Platform, while PT Rajawali Swiber Cakrawala is responsible for the engineering and laying of the 2 sub-sea pipelines as well as the transportation and installation of the 2 platforms in water depth of 82 metres.

Construction work on the platforms is expected to commence in July 2012 with offshore completion by September 2013.

Mr Norman Chew, President Director of PT SMOE Indonesia said “Both PT SMOE and PT Rajawali Swiber Cakrawala recognise each other’s strength and we are glad to have joined forces to secure this contract. This is the second contract award that PT SMOE Indonesia has secured from Premier Oil Natuna Sea B.V.”

[mappress] Offshore Energy Today Staff, June 4, 2012

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1
  2. 2
  3. 3
  4. 4

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free