UK: Work on Teesside Offshore Wind Farm Progresses Well

The installation of transition pieces is nearing completion on the Teesside offshore wind farm. The 22nd yellow coloured transition piece was recently installed with work underway on the next. The transition pieces sit on top of all the 27 foundation monopiles. Elsewhere, work has also started on th

1 minutes read

The installation of transition pieces is nearing completion on the Teesside offshore wind farm. The 22nd yellow coloured transition piece was recently installed with work underway on the next.

The transition pieces sit on top of all the 27 foundation monopiles. Elsewhere, work has also started on the installation and burial of inter array subsea cables.

Once complete, the next phase of work will be the actual installation of the turbine towers and blades. Weather permitting, the project remains set for completion before the end of 2012.

[mappress]

Press release, October 9, 2012; Image: Van Oord

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.