MEO Australia provided an update in relation to the Gurame SE-1X well being drilled offshore North Sumatra in the Seruway PSC using the Hercules #208 drilling rig.
Since the last report, the 12¼” hole was sidetracked from 2,099mMDRT to 2,681mMDRT. At 0200 hrs Jakarta time on 29th October the 95/8” casing had been run to 1,478mMDRT.
The forward plan is to complete running and cementing the 95/8” casing prior to drilling out to the first objective the Baong sands.
[mappress] LNG World News Staff, October 29, 2012; Image: MEO