Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Subsea›VIDEO: O-lay Pipeline Installation Method Presented
Subsea

April 9, 2013 · about 13 years ago

VIDEO: O-lay Pipeline Installation Method Presented

O-lay is a state-of-the-art disruptive method to install offshore pipeline in a safe way and with a minimum of costs. The method has following stages: Welding and construction onshore, pulling the pipe in the water supported by floatation devices, spiraling the pipe in a flat mono-layer spiral on th

2 minutes read
  • LinkedIn
  • X
  • Email

O-lay is a state-of-the-art disruptive method to install offshore pipeline in a safe way and with a minimum of costs.

The method has following stages: Welding and construction onshore, pulling the pipe in the water supported by floatation devices, spiraling the pipe in a flat mono-layer spiral on the surface of the water while the steel remains in its elastic area (this is the “O” in O-lay) , transportation of the spiral towards the location where it has to be laid. Finally the pipe is laid to the bottom with the help of a simple but specially designed lay barge.

The laying is done with a type of S-lay where the pipe will leave the barge at an end position or through the center of the barge which will give the barge a better stability and a better floating support.This means that the pipe can be laid deeper with a lighter barge.

When the spiral is made the method makes use of special bending method whereby at certain intervals “points of inflection” are applied. These points are actual end points of anchor lines in the outer circumference of the ‘spiral to be made’. The method can also be used to retrieve pipe from the sea bottom. Instead of the anchor lines, the method makes use of small but powerful boats which are then attached to the pipeline for creating the perfect circle. All boats are attached to a dynamic positioning system that will “coordinate” the whole operation.

With this method pipes can be laid in very shallow water (some meters of depth whereby a special pontoon will be used) and very deep water (several thousands of meters with the aid of a lay barge)

Due to the fact that almost all work is prepared onshore (including welding and inspecting the pipe) the pipe can be installed at a speed of 25 km per day.

[mappress] Subsea World News Staff, April 9, 2013; Image: o-lay.net

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

SubseaEquipmentOperations & Maintenance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Methanol-ready energy subsea construction vessel arrives in Norway for completion
  2. 2Equinor employs 2009-built Odfjell Drilling rig for additional wells
  3. 3Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection
  4. 4More oil found at permit offshore Gabon

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free