Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Subsea›DONG Energy: Hejre Jacket Construction Progresses
Subsea

January 2, 2014 · about 13 years ago

DONG Energy: Hejre Jacket Construction Progresses

In Vlissingen, the Netherlands, the employees at the Heerema yard are working hard to finish the construction of the Hejre jacket in time for the planned installation in the North Sea, in the early summer of 2014. The Hejre development is an important step for E&P on its way to reaching its targets

2 minutes read
  • LinkedIn
  • X
  • Email

In Vlissingen, the Netherlands, the employees at the Heerema yard are working hard to finish the construction of the Hejre jacket in time for the planned installation in the North Sea, in the early summer of 2014.

The Hejre development is an important step for E&P on its way to reaching its targets of doubling the oil and gas production by 2020.

The construction of the jacket started by assembling and welding together hundreds of smaller structural components into rows. The first pair of rows was joined by bracings and crossings and forms a 90-metre long and 30-metre high box structure.

More than 80% complete

More than 80% of the work tasks for the jacket have already been finished, but the major elements still have to be fitted together.

93 metres high and the width of a football pitch, the jacket will weigh 8,000 tonnes when installed.

On 18 December, the third row the 1,000 tonnes heavy row 2, which was welded together next to the box structure, was ready to be tilted from horizontal to vertical position in a ‘roll up’ operation.

Four heavy cranes, two with a capacity of more than 310 tonnes each, were aligned to lift the one side of the row, and the other side should rotate in the teflon-support guides already prepared.

In a 4-hour long lifting process, the outer side of the row was lifted – slowly bit by bit – while the cranes moved in a co-ordinated procedure after Row 2 turned upwards slowly. With less than 15 degrees left, heavy stationary winches took over, and in a very controlled movement the wires pulled the row to its vertical position.

By mid-January 2014, the final row will be rolled up in a similar process, making the structure look like the real jacket. Once these operations have been completed, the jacket weight will have increased to almost 7000 tonnes.

Press Release, January 02, 2014; Image: DONG Energy

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

SubseaBusiness & FinanceEquipment

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Woodside passes the baton for offshore gas project to Timor Gap in $200 million deal
  2. 2Fugro wins UXO survey contract for German offshore grid connections
  3. 3Accelerating operational excellence in offshore energy
  4. 4Go-ahead for North Sea wildcat clears path for Equinor’s drilling ops with COSL rig

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free