Final Train 1 GLNG Modules Arrive in Gladstone (VIDEO)

The Santos GLNG project has reached another key milestone with the final three modules for Train 1 arriving on site last week. This content is available after accepting the cookies. Change cookie-settings View on Youtube. The structures, all cryogenic modules, weigh a total of 2,777 tonnes and will

1 minutes read

The Santos GLNG project has reached another key milestone with the final three modules for Train 1 arriving on site last week.

The structures, all cryogenic modules, weigh a total of 2,777 tonnes and will form part of the LNG train’s liquefaction system.

Train 1 is made up of 82 modules and it has taken close to two years to construct and transport these components to Curtis Island.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.