The Santos GLNG project has reached another key milestone with the final three modules for Train 1 arriving on site last week.
The structures, all cryogenic modules, weigh a total of 2,777 tonnes and will form part of the LNG train’s liquefaction system.
Train 1 is made up of 82 modules and it has taken close to two years to construct and transport these components to Curtis Island.