Picture of the Day: GLNG Jetty

Santos said today that the GLNG jetty is over 95% complete with the installation of quick release mooring hooks and fenders complete, and installation of the gangway tower and pre-commissioning works commenced. Overall, the GLNG project is 80% complete and remains on track for first LNG in 2015. [ma

1 minutes read

Santos said today that the GLNG jetty is over 95% complete with the installation of quick release mooring hooks and fenders complete, and installation of the gangway tower and pre-commissioning works commenced.

Overall, the GLNG project is 80% complete and remains on track for first LNG in 2015.

[mappress]

LNG World News Staff, April 17, 2014; Image: Santos

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.