Sabine Pass LNG: Stage 1 Construction 63.3 Pct Complete

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through March at the Sabine Pass LNG terminal, located in Cameron Parish, Louisiana. Stage 1 (trains 1 and 2) engineering is 96.0% complete, procurement is 94.6%, and subcontract and direct

1 minutes read

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through March at the Sabine Pass LNG terminal, located in Cameron Parish, Louisiana.

Stage 1 (trains 1 and 2) engineering is 96.0% complete, procurement is 94.6%, and subcontract and direct hire construction work are 37.7% and 21.0% complete, respectively. Stage 1 overall project completion is 63.3% against the plan of 65.1%.

Stage 2 (trains 3 and 4) engineering is now 55.3% complete, procurement is 44.6%, and subcontract and direct hire construction work are 14.0% and 0.6% complete, respectively. Overall project completion for Stage 2 is 27.1% against the plan of 24.5%.

Actual project progress continues to support the achievement of the scheduled substantial completion dates for trains 1 and 2, which remain as February 2016 and June 2016, respectively.

Trains 3 and 4 substantial completion dates are April 2017 and August 2017.

[mappress] LNG World News Staff, April 23, 2014; Image: Sabine Pass LNG

Advertisement

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.