Sabine Pass LNG: stage 1 construction 71.8 pct complete

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through July at the Sabine Pass LNG terminal, located in Cameron Parish, Louisiana. Stage 1 (trains 1 and 2) engineering is 99.4% complete, procurement is 99.5%, and subcontract and direct

1 minutes read

Sabine Pass LNG, a unit of Cheniere Energy, filed a report with the U.S. FERC covering construction activities through July at the Sabine Pass LNG terminal, located in Cameron Parish, Louisiana.

Stage 1 (trains 1 and 2) engineering is 99.4% complete, procurement is 99.5%, and subcontract and direct hire construction work are 46.6% and 35.6% complete, respectively, for the period. Stage 1 overall project completion is 71.8% against the plan of 72.5%.

Stage 2 (trains 3 and 4) engineering is 81.3% complete, procurement is 58%, and subcontract and direct hire construction work are 24.7% and 5.1% complete, respectively. Overall project completion for stage 2 is 38.5% against the plan of 36.3%.

Actual project progress continues to support the achievement of the scheduled substantial completion dates for trains 1 and 2, which remain as February 2016 and June 2016, respectively.

Trains 3 and 4 substantial completion dates are April 2017 and August 2017.

LNG World News Staff, August 25, 2014; Image: Sabine Pass LNG

Advertisement

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.