Advertisement

Dredging

about 11 years ago

VIDEO: Liverpool2 Scheme on Track

Peel Ports Group has just released a video about the Liverpool2 project, their new $500 million container terminal being built at the Port of Liverpool. Contractors Bam Nuttall and Van Oord have completed the first phase of the infilling, using 1.43 million tonnes of sand and silt deposited from dre

1 minutes read

Peel Ports Group has just released a video about the Liverpool2 project, their new $500 million container terminal being built at the Port of Liverpool.

Contractors Bam Nuttall and Van Oord have completed the first phase of the infilling, using 1.43 million tonnes of sand and silt deposited from dredged material.

The piling process, which began in 2014 and is due to be completed in the next few months, involves drilling from large jack-up rigs and inserting tubular piles to create a new 854m long quay wall.

The area behind the wall has been dredged to bed rock to allow for virgin materials to be deposited.

Other significant elements of the project to date include:

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.