Bladt: Second Gode Wind 1 TP Batch Sets Sail

On Friday 19 June, the 2nd load out of the 55 transition pieces (TP) for the Gode Wind 1 project was completed from Bladt Industries’ quayside in Aalborg. The load out was carried out by Bladt and after leaving Aalborg, the 500 tonnes heavy transition pieces were sailed to Eemshaven in the Netherlan

1 minutes read

On Friday 19 June, the 2nd load out of the 55 transition pieces (TP) for the Gode Wind 1 project was completed from Bladt Industries’ quayside in Aalborg.

The load out was carried out by Bladt and after leaving Aalborg, the 500 tonnes heavy transition pieces were sailed to Eemshaven in the Netherlands.

The Gode Wind project is owned by DONG Energy and consists of a total of 97 foundations divided into two lots. The 13th and last load out of the 42 transition pieces for the Gode Wind 2 project was finished on Tuesday 9 June.

During the next couple of months, load out of the remaining transition pieces for Gode Wind 1 will be executed from Bladt’s facilities in Aalborg.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.