Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Butendiek OWF Up and Running
Wind Farms

August 5, 2015 · about 11 years ago

Butendiek OWF Up and Running

By bringing the 80th and thus final wind turbine into operation, wpd has completed the construction of the 288 MW Butendiek offshore wind farm, which is now in full operation. Wpd, the Bremen wind developer and operator is responsible for the construction and operation phases. The Butendiek offshore

1 minutes read
  • LinkedIn
  • X
  • Email

By bringing the 80th and thus final wind turbine into operation, wpd has completed the construction of the 288 MW Butendiek offshore wind farm, which is now in full operation.

Wpd, the Bremen wind developer and operator is responsible for the construction and operation phases.

The Butendiek offshore wind farm is jointly owned by wpd, Marguerite Fund, Siemens Financial Services, Industriens Pension, Pensionskassernes Administration (PKA), CDC Infrastructure and ewz (Elektrizitätswerk der Stadt Zürich).

Offshore works began in March 2014. All foundations, cables and the substation were installed according to schedule during the last year. Mid-June, the last wind turbine was installed.

“Already eleven months after start of construction, the first wind turbine fed electricity into the public grid. This makes Butendiek the fastest established offshore project,” says project director Martin Lehnhoff .

Achim Berge Olsen, Managing Director of OWP Butendiek GmbH & Co. KG and wpd offshore GmbH said: “The lowest value has been measured regarding noise emissions during installation and the 1.3 bn euro OWF Butendiek project has been completed on schedule and within budget. From now on, OWF Butendiek is able to supply 370,000 households with green energy.”

Image: Marguerite

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsNews

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1TGS on 3D imaging mission to unlock new insights into Malaysia's offshore discovery
  2. 2Petrobras strikes another oil-bearing zone in Equatorial Margin frontier
  3. 3MidOcean gets hold of $4 billion in major capital raise to fuel global LNG push
  4. 4BP taking the wheel of Namibian license trio as farm-in deal clear final regulatory gate

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free