Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›ABS Flags Safety Issues in Deepwater Wind’s Construction
Wind Farms

September 14, 2015 · about 11 years ago

ABS Flags Safety Issues in Deepwater Wind’s Construction

The developer of US first offshore wind farm, Deepwater Wind, is making some safety changes after an independent consultant has identified several health and safety issues. ABS Group, a Houston-based firm listed several concerns during the construction of five foundations at the 30MW Block Island of

1 minutes read
  • LinkedIn
  • X
  • Email

The developer of US first offshore wind farm, Deepwater Wind, is making some safety changes after an independent consultant has identified several health and safety issues.

ABS Group, a Houston-based firm listed several concerns during the construction of five foundations at the 30MW Block Island offshore wind farm.

In the report for Rhode Island Coastal Resources Management Council, ABS highlighted near misses including dropped objects, personnel working under suspended loads, personnel transfers, rescue skiff reliability and loss of control of suspended load as some of the safety issues.

ABS also named the limited offshore experience among employees with Deepwater’s contractors at New Jersey-based Weeks Marine and Seattle-based Manson Construction.

“We agreed with those recommendations, and our offshore contractor is implementing them,” said Deepwater Wind in a statement. “For example, the contractor will dedicate more full-time, dedicated safety personnel to all work shifts.”

The foundations installation started in late July. Soon after, one of the foundations was damaged due to collision with a construction barge, after which it was removed and shipped to New Jersey for repair.

Deepwater Wind is confident that despite these setbacks, the project is on schedule to go into operation in the fall of 2016.

OffshoreWIND staff: Image: Deepwater Wind

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsNews

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free