Two 685 MVA power transformers have been delivered and installed in the land-based converter station Dörpen West, which is part of the DolWin3 project. The power transformers have been developed, manufactured and tested according to the specific needs of the project at GE’s site in Mönchengladbach.

1 minutes read

Two 685 MVA power transformers have been delivered and installed in the land-based converter station Dörpen West, which is part of the DolWin3 project.

The power transformers have been developed, manufactured and tested according to the specific needs of the project at GE’s site in Mönchengladbach.

The DolWin3 project, the third network connection in the DolWin wind farm cluster in southwestern North Sea, is on schedule and should be completed in 2017, TenneT reported.

The offshore grid connection project has a capacity of 900MW for the integration of wind energy into the German transmission network. Completion of the project will enable the supply of around one million households in Germany with clean energy.

Offshore WIND Staff

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.