Siem Offshore to Install Nordsee One Inter-Array Cables by End of August

Siem Offshore’s recent additions to the fleet, the installation support vessel Siem Moxie and the cable lay vessel Siem Aimery, are expected to install all of the 59 inter-array grid cables for the 332MW Nordsee One offshore wind farm by the end of August. Siem Offshore Contractors GmbH (SOC), a who

1 minutes read

Siem Offshore’s recent additions to the fleet, the installation support vessel Siem Moxie and the cable lay vessel Siem Aimery, are expected to install all of the 59 inter-array grid cables for the 332MW Nordsee One offshore wind farm by the end of August.

Siem Offshore Contractors GmbH (SOC), a wholly owned subsidiary of Siem Offshore, won a contract for the turnkey supply and installation package of the inter-array grid cable system for the Nordsee One in April 2014.

The wind farm’s 54 6.15MW turbines will be connected to the offshore substation by ten strings of cables with an overall length of approximately 70 kilometres.

Nordsee One is owned by Northland Power Inc. (85%) and RWE Innogy GmbH (15%). The wind farm is located approximately 40 kilometres north of the island of Juist in the German part of the North Sea.

The commissioning of the wind farm is scheduled for 2017.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.