Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Harwich International Port Tipped For Galloper O&M Base
Wind Farms

November 4, 2016 · about 10 years ago

Harwich International Port Tipped For Galloper O&M Base

Galloper Wind Farm Limited (GWFL) has agreed a lease in principle with Harwich International Port for an Operations & Maintenance (O&M) base for the 336MW Galloper offshore wind farm. GWFL is currently pursuing planning permission in relation to this, Toby Edmonds, Project Director, Galloper Wind Fa

1 minutes read
  • LinkedIn
  • X
  • Email

Galloper Wind Farm Limited (GWFL) has agreed a lease in principle with Harwich International Port for an Operations & Maintenance (O&M) base for the 336MW Galloper offshore wind farm.

GWFL is currently pursuing planning permission in relation to this, Toby Edmonds, Project Director, Galloper Wind Farm, said.

“Following the redesign of the project in 2015 we considered a number of options in relation to the Operations & Maintenance base and Harwich meets the project’s specific requirements,” Edmonds said.

”Galloper Wind Farm is also supported by our Offshore Construction Coordination Base at the Port of Lowestoft, our onshore substation base in Sizewell, and the turbine assembly base, currently in construction, at Great Yarmouth.”

Galloper is an extension of the existing and fully operational Greater Gabbard wind farm off the coast of Suffolk. The wind farm will comprise 56 Siemens wind turbines, each with a capacity of 6MW, installed some 27km off the coast.

The offshore construction phase started in June 2016 and is expected to be completed in late 2017. The wind farm is expected to commence operations in March 2018.

The wind farm is being constructed by innogy on behalf of the GWFL, a GBP 1.5 billion joint equity partnership of 25% each between innogy UK, UK Green Investment Bank, Siemens Financial Services and Macquarie Capital.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsOperations & Maintenance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  2. 2TotalEnergies earmarks annual spend of up to $17 billion over next five years
  3. 3Fugro performs ultra-deepwater AUV survey off East Malaysia
  4. 4Southeast Asian oil field development clears key environmental hurdle to move toward FID

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free