Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Marine Energy›ORPC makes effort to keep Maine tidal project afloat
Marine Energy

March 24, 2017 · about 9 years ago

ORPC makes effort to keep Maine tidal project afloat

Ocean Renewable Power Company (ORPC) has applied to Maine regulators for the amendment of a contract with Emera Maine in an effort to save the 20-year power purchase agreement.

2 minutes read
  • LinkedIn
  • X
  • Email

Ocean Renewable Power Company (ORPC) has applied to Maine regulators for the amendment of a contract with Emera Maine in an effort to save the 20-year power purchase agreement.

ORPC’s subsidiary, ORPC Maine, has made a request to the State of Maine Public Utilities Commission to allow ORPC’s tidal generator to be offline for 90 months, instead of 48, initially agreed with Emera Maine under a power purchase agreement.

The 20-year power purchase contract, agreed between ORPC and Emera Maine, was approved by the Commission on December 21, 2012.

The US-based tidal energy developer was to provide power from its TidGen turbine generator unit, installed in Cobscook Bay, Maine, which operated successfully until April 21, 2013, when the device experienced salt-water infiltration, which caused the power system to cease operations.

ORPC retrieved the TidGen unit later in 2013, but failed to fix the device due to issues with suppliers as there were no commercially available generators required for the TidGen device, which meant the replacement generator needed to be specifically manufactured for the device.

After several failed attempts to obtain the new generator, ORPC hired Rolls-Royce Marine to build the generator, for which the factory acceptance tests are scheduled for early or mid-2017.

However, since the current agreement with Emera Maine expires on April 21 this year, and ORPC will not be able to resume the delivery of energy until mid-2019, exceeding the agreed 48 months period, the company has asked for the amendment of the original contract.

In the document filed with Maine’s regulator, ORPC said that Emera Maine does not object to the amendment and will execute the it should it be approved by the Commission.

The response from the Commission is expected before April 21, 2017.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Marine EnergyAuthorities & GovernmentBusiness & FinanceOperations & MaintenanceResearch & DevelopmentTechnology

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Venture Global and ConocoPhillips play the long game with 20-year LNG pact
  2. 2Egypt and Chevron seal Mediterranean oil & gas exploration deal
  3. 3Subsea battery system for offshore wind completes test before deployment
  4. 4$125M purchase: New owner to take over 178-meter subsea vessel next October

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free