Oceanside Dredging Halted Due to Weather and Equipment Issues

The U.S. Army Corps of Engineers, Los Angeles District, has just released its latest update on the Oceanside Harbor dredging scheme, saying that the operations halted May 8 due to weather and equipment issues. A total of 53,000 cubic yards of sediment has been dredged to date. The contract calls for

1 minutes read

The U.S. Army Corps of Engineers, Los Angeles District, has just released its latest update on the Oceanside Harbor dredging scheme, saying that the operations halted May 8 due to weather and equipment issues.

A total of 53,000 cubic yards of sediment has been dredged to date. The contract calls for a total of 430,000 cubic yards of sediment to be removed from the entrance channel and placed on Oceanside beaches.

USACE awarded the contract to Manson Construction Company of Seattle, Washington, on March 13.

The U.S. Army Corps of Engineers, Los Angeles District, dredges this entrance channels on annual basis in order to maintain the federally authorized depth necessary to accommodate the military, commercial and private vessels that use the harbors.

[mappress mapid=”24053″]

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.