Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Miami Harbor Deepening Post-Construction Report Released
Dredging

May 18, 2017 · about 9 years ago

Miami Harbor Deepening Post-Construction Report Released

The U.S. Army Corps of Engineers, Jacksonville District, has just released the Miami Harbor Deepening Project one-year post-construction assessment for hard-bottom middle and outer reef benthic communities. The report includes data relevant to an assessment of temporary and permanent project effects

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Jacksonville District, has just released the Miami Harbor Deepening Project one-year post-construction assessment for hard-bottom middle and outer reef benthic communities.

The report includes data relevant to an assessment of temporary and permanent project effects at channel-side sites as per the Florida Department of Environmental Protection (FDEP) permit conditions for construction.

According to the Corps, the overarching goal of the monitoring plan is to assess status and trends of physical (e.g. sedimentation) and biological responses to construction activities.

Scientists compared the Miami Harbor project’s one-year post construction surveys with baseline surveys at 19 permanent monitoring stations located at channel-side locations and control sites. The FDEP identified the permanent monitoring stations.

The report focuses on impacts to channel-side hard-bottom communities, including corals, octocorals, sponges and other benthic invertebrates. Scientists studied thousands of photos and videos, and hundreds of hours of dive-time observations from more than 7,000 dives.

USACE is awaiting data relevant to potential effects of project sedimentation on hard-bottom communities outside the channel. Results are anticipated in late summer.

The report highlights:

Next Steps:

This is one of two assessment surveys for the project site. The other survey is designed to assess impacts that may have occurred farther afield than the channel side locations. The Corps is also conducting a sediment tracer study that is key to potentially drawing conclusions to the status and trends of the physical environment. Officials anticipate those study results in the fall.

Once all data collection and assessments are complete, the Corps will continue to work in partnership with FDEP and National Marine Fisheries Services to analyze the data and determine the permanent, as opposed to transient, effects of the deepening project, the success of the mitigation efforts, and the need, if any, for additional mitigation.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1QatarEnergy locks in more US LNG through 20-year deal with Woodside
  2. 2CETO wave energy unit to hit the water in November
  3. 3North Sea gas discovery twice as big after appraisal success with tie-back on the table
  4. 4Huge investment to keep first UK-France interconnector running until at least 2050

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free