Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›PHOTO: Installing Geotextile Fabric at Clouter Creek Disposal Area
Dredging

May 30, 2017 · about 9 years ago

PHOTO: Installing Geotextile Fabric at Clouter Creek Disposal Area

The U.S. Army Corps of Engineers, Charleston District, is currently installing a Geotextile Fabric at the Clouter Creek Disposal Area with the main goal to increase strength of the base of the dike foundation. This work will allow for increased resiliency and the capability to raise the elevation of

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Charleston District, is currently installing a Geotextile Fabric at the Clouter Creek Disposal Area with the main goal to increase strength of the base of the dike foundation.

This work will allow for increased resiliency and the capability to raise the elevation of the dike in the future in order to store more dredged material.

The project marks the life cycle phases of the Clouter Creek Disposal Area that is managed by USACE’s Charleston District.

The life cycle begins with dredging, which is when mud and sand, also known as dredge material, is sucked from the bottom of the Cooper River and transported through a pipe and pumped into the disposal cells.

During this process it looks like a lake. Over time, the mud and sand drop out of the water and the water is released at a controlled rate back into the Cooper River.

Next is the drying phase, which takes about 8-12 months for the water to drain, USACE said.

Finally, the last phase is diking; after several cycles of ditching the mud, the mixture is dry enough to dig out and use to make the dikes higher, which allows for more mud mixture to be put back into the cell.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1First-of-its-kind marine robotics test and development center opens in Norway
  2. 2Shell ups its production ante with first oil from US Gulf project’s third chapter
  3. 3Germany’s SEFE firms up two-decade-long offtake deal with Canadian LNG project
  4. 4Baker Hughes' subsea systems to help fast-track Cyprus's first commercial gas project

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free