Cheniere’s Corpus Christi LNG project 72.4 percent done (Gallery)

Cheniere’s Corpus Christi liquefaction project located on the U.S. Gulf Coast has reached 72.4 percent completion.

1 minutes read

Cheniere’s Corpus Christi liquefaction project located on the U.S. Gulf Coast has reached 72.4 percent completion.

According to the Houston-based LNG player’s monthly report, the engineering has reached 100 percent completion, procurement reached 89.4 percent, while subcontract and direct hire construction work reached 49.4 percent and 49.2 percent completion, respectively.

Cheniere noted that the jobsite was closed from August 24 to September 10, due to the Hurricane Harvey, with construction resuming with permanent plant concrete, structural steel, aboveground pipe, electrical and equipment installation.

Earlier this month, Cheniere made a decision to switch the planned two large-scale liquefaction trains of the project for seven mid-scale trains.

The change would increase the planned output from 9 million tons per annum to 9.5 mtpa with electric instead of compressor engines to be used for the proposed compressor modifications.

With the change, the project would have an aggregate nominal capacity of 23 mtpa.

Advertisement

Cheniere noted in its monthly filing to the Federal Energy Regulatory Commission that activities planned for the month of October 2017 are on track.

LNG World News Staff

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.