Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Phase 2 of the Perry Barr Scheme Underway
Dredging

March 19, 2018 · about 8 years ago

Phase 2 of the Perry Barr Scheme Underway

The Environment Agency has begun works on the on phase 2 of the Perry Barr and Witton flood risk management scheme. According to the EA, the scheme will provide additional flood storage at Forge Mill in Sandwell Valley which lies upstream of Perry Barr and Witton and will control the passage of floo

1 minutes read
  • LinkedIn
  • X
  • Email

The Environment Agency has begun works on the on phase 2 of the Perry Barr and Witton flood risk management scheme.

According to the EA, the scheme will provide additional flood storage at Forge Mill in Sandwell Valley which lies upstream of Perry Barr and Witton and will control the passage of flood water downstream.

Until May 2018, work will continue on preparing for the main scheme construction to start. The main aspects of this phase include the building of the new embankment, installation of the river outlet and temporary re-diverting the river.

“ To increase the amount of flood water we can store in the Sandwell Valley, we will build a new embankment to the east of the existing lake. The embankment will run from north to south and cross the river channel, ” said the Environment Agency .

“ Where it crosses the river an outlet structure will be installed, along with a spillway, allowing us to manage the flow of water when necessary. When river levels rise, the gates of the outlet structure will be closed, stopping water from flowing downstream and storing it behind the new embankment ,” added the EA.

Phase 1 of the scheme was completed in spring 2017, bringing a new flood wall and flow conveyance improvements through Witton and down to Witton Gravelly Industrial Estate.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Methanol-ready energy subsea construction vessel arrives in Norway for completion
  2. 2Equinor employs 2009-built Odfjell Drilling rig for additional wells
  3. 3Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection
  4. 4More oil found at permit offshore Gabon

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free