Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Oceanside Harbor Dredging Work Set for Fall
Dredging

August 27, 2018 · about 8 years ago

Oceanside Harbor Dredging Work Set for Fall

The U.S. Army Corps of Engineers’ Los Angeles District said in their latest release that they plan to dredge Oceanside Harbor this fall. Manson Construction, the USACE’s contractor, will begin the work in October after environmental restrictions – which include dredging during the California least t

1 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers’ Los Angeles District said in their latest release that they plan to dredge Oceanside Harbor this fall.

Manson Construction, the USACE’s contractor, will begin the work in October after environmental restrictions – which include dredging during the California least tern nesting season – have ended.

“ The California least tern – an endangered subspecies – can be present in the area through September. Dredging, habitat loss, nesting disturbance, pollution and predation by domestic and wild animals are all threats to the species ,” USACE said.

Survey crews have been monitoring the harbor’s entrance channel on a periodic basis to ensure sufficient depth for safe navigation. Results from a July 30 survey indicated a significant amount of shoaling around the south jetty tip, and the western portion of the entrance channel was at a depth of 16 feet.

Cost of the fall dredging is about $3.5 million.

Last year, Manson Construction successfully removed 440,000 cubic yards of beach-quality sand from the harbor and placed it along Oceanside’s beaches. Typical years see an average of about 250,000 cubic yards, said USACE.

Material dredged from the entrance channels is placed along Oceanside’s beaches. Placement of beach-quality material along the shoreline is a beneficial byproduct of the maintenance dredging project.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Connecting the offshore energy industry through smarter travel
  2. 2Borr Drilling’s rig trio lines up jobs in Africa and Europe
  3. 3Inpex broadens its Southeast Asian horizons with two offshore blocks
  4. 4Dutch LNG terminal capacity rises to 20 billion cubic meters with 4th tank

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free