Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Clean Fuel›Nord Stream 2 pipelay work starts in Finland
Clean Fuel

September 6, 2018 · about 8 years ago

Nord Stream 2 pipelay work starts in Finland

The offshore pipelay vessel Solitaire, owned by Allseas, started on Wednesday the pipelay for the Nord Stream 2 natural gas pipeline in the Gulf of Finland. Gazprom-operated Nord Stream 2 will link Russia and Germany, supplying Russian natural gas to Europe. Before the start of pipelay, Solitaire wa

2 minutes read
  • LinkedIn
  • X
  • Email

The offshore pipelay vessel Solitaire, owned by Allseas, started on Wednesday the pipelay for the Nord Stream 2 natural gas pipeline in the Gulf of Finland.

Gazprom-operated Nord Stream 2 will link Russia and Germany, supplying Russian natural gas to Europe.

Before the start of pipelay, Solitaire was equipped and tested to meet the project’s “strict” requirements.

“Nord Stream 2’s construction plan takes into consideration different construction conditions, in particular environmental requirements,” Gazprom said in a statement.

Solitaire for example uses a dynamical positioning system with thrusters to position itself accurately. It is thus only the pipeline that touches the seabed. Using a vessel operating without anchors ensures additional safety in the congested Gulf of Finland.

Solitaire is a 300-meter-long and 41-meter-wide vessel that will lay pipes around the clock seven days a week.

The vessel has accommodation on board for 420 persons. Pipe supply vessels (PSVs) will deliver the 12-meter, 24-ton pipes used to build Nord Stream 2 to the pipelay vessel from the project’s nearest logistics hubs, such as Kotka or Hanko, to maintain the necessary pipe stock.

The pipes are welded together on board the vessel, then welds are tested and finally the pipeline is lowered down to the seabed. A survey vessel will perform surveys prior to and after pipelay to verify that the pipeline is located at its correct position.

The safety zone around the pipelay vessel is 1.85 kilometers (1 nautical mile) and around the survey vessels Oceanic and Olympic Triton 500 meters (0.3 nautical miles).

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Clean FuelNews

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Woodside passes the baton for offshore gas project to Timor Gap in $200 million deal
  2. 2Fugro wins UXO survey contract for German offshore grid connections
  3. 3Accelerating operational excellence in offshore energy
  4. 4Go-ahead for North Sea wildcat clears path for Equinor’s drilling ops with COSL rig

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free