Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›MHI Vestas Orders Two New Esvagt SOVs
Offshore Wind

September 17, 2018 · about 8 years ago

MHI Vestas Orders Two New Esvagt SOVs

Esvagt has won two long-term contracts by MHI Vestas to deliver two new service operation vessels (SOVs) for the Borssele III & IV offshore wind project in the Netherlands and Triton Knoll in the UK.

2 minutes read
  • LinkedIn
  • X
  • Email

Esvagt has won two long-term contracts by MHI Vestas to deliver two new service operation vessels (SOVs) for the Borssele III & IV offshore wind project in the Netherlands and Triton Knoll in the UK.

The contracts will run for up to 15 years. An option for an additional SOV for servicing the Moray East offshore wind farm in the UK is also included.

According to Esvagt, the agreements reinforce the relationship between the two companies, who have collaborated on the Belwind 1 and Nobelwind 1 offshore wind projects in Belgium since 2010. The newly-built SOV Esvagt Mercator commenced its charter at the two wind farms in 2017.

The new SOVs will feature an 831L design, on which Esvagt is collaborating with Norwegian Havyard. The 70.5m long vessels will be equipped with a compensated walk-to-work gangway and daughter craft, as well as multiple other features, and will have the capacity to accommodate up to 60 persons.

“We are proud to continue our close partnership, and together with MHI Vestas set the standard for innovation and long-term solutions. We look forward to presenting 831L as yet another customized SOV, in which we combine the client’s needs with our competencies and experience in order to guarantee the most optimal and cost-efficient solution,” said Søren Karas , CCO at ESVAGT.

The 731.5MW Borssele III & IV wind farm will comprise 77 MHI Vestas V164 9.5MW turbines. The project recently achieved financial close, enabling the developers to focus on the construction phase, with the main offshore works due to start in the fourth quarter of 2019.

Triton Knoll will comprise 90 MHI Vestas 9.5MW turbines. Onshore construction commenced earlier this month, while offshore construction is expected to start in late 2019 or early 2020.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindOperations & MaintenanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Methanol-ready energy subsea construction vessel arrives in Norway for completion
  2. 2Equinor employs 2009-built Odfjell Drilling rig for additional wells
  3. 3Nexans starts manufacturing 525 kV subsea cables for LanWin2 offshore wind grid connection
  4. 4More oil found at permit offshore Gabon

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free