Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›News›Irregularities found during Ivar Aasen control room probe
News

October 4, 2018 · about 8 years ago

Irregularities found during Ivar Aasen control room probe

The PSA has found irregularities during an audit of Aker BP and the control room solution for the Ivar Aasen platform.

2 minutes read
  • LinkedIn
  • X
  • Email

Norwegian offshore safety watchdog, the Petroleum Safety Authority (PSA), has found irregularities during an audit of Aker BP and the control room solution for the Ivar Aasen field.

The PSA said on Thursday that the objective of the audit, conducted on August 21, was to verify whether the implementation of the selected solution with a control room in Trondheim was prudent and in compliance with regulations.

The audit by the safety body identified a non-conformity in connection with the emergency shutdown system.

PSA also found improvement points in connection with risk reduction and continuous improvement, the emergency preparedness analysis, communication analyses, and the security analysis.

The safety watchdog told Aker BP to report on how the non-conformity and improvement points would be addressed by October 26, 2018.

Ivar Aasen

Discovered in 2008, the Ivar Aasen field is located in the northern part of the North Sea, about 175 km west of Karmøy. The water depth is about 110 meters. It contains around 186 million barrels of oil equivalent (boe).

The field started oil production on Christmas Eve, December 24, 2016 , four years after the Plan for Development and Operation (PDO ) was submitted to Norwegian authorities.

It was developed as a stand-alone platform for partial processing and water conditioning and injection, with transfer of the multiphase hydrocarbon mixture through two pipelines to the neighbouring Edvard Grieg field for final processing and export.

The economic life of the Ivar Aasen field may be 20 years, depending on oil prices and production development.

The partners in the field are Aker BP with 34.7862% interest, Equinor with 41.4730%, Bayerngas Norway with 12.3173%, Wintershall Norway with 6.4651%, VNG Norge with 3.0230%, Lundin Norway with 1.3850%, and Okea with 0.5540% interest.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

News

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Saipem and Egypt’s MDC seal pact to target MENA offshore drilling market
  2. 2FEED job for Barents Sea FPSO topsides goes to Aibel
  3. 3Cook Inlet LNG steps up Alaska energy push with TDI-Brooks survey
  4. 4Nexans, Red Eléctrica to tie Mallorca and Menorca closer with new Balearic power link

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free