Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Subsea›Claxton to Work on Deep Panuke Decom Project
Subsea

October 17, 2018 · about 8 years ago

Claxton to Work on Deep Panuke Decom Project

Claxton has won a contract to provide high-pressure riser and abrasive jet cutting services to the Deep Panuke decommissioning project offshore Canada. The gas field is about 250 km southeast of Halifax, Nova Scotia, on the Scotian Shelf. Deep Panuke field ceased production in May 2018 and the opera

1 minutes read
  • LinkedIn
  • X
  • Email

Claxton has won a contract to provide high-pressure riser and abrasive jet cutting services to the Deep Panuke decommissioning project offshore Canada.

The gas field is about 250 km southeast of Halifax, Nova Scotia, on the Scotian Shelf. Deep Panuke field ceased production in May 2018 and the operator has begun planning facility and well decommissioning activities.

For this major project, Claxton is supplying a high-pressure subsea drilling riser system with associated services in a shallow-water programme to connect the surface blowout preventer stack on the rig with subsea horizontal trees. Claxton’s SABRE subsea abrasive jet cutting system will then perform well severance 3 m below the mudline.

The work will be undertaken on five subsea wells from the harsh environment offshore, jackup drilling rig Noble Regina Allen, which has been engaged by the project operator.

The well plug-and-abandonment programme is expected to start in January 2020. The running, operation and pulling of the riser on each well will take about 25 days and will be followed by the cutting phase. The campaign is expected to finish in mid-July 2020.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

SubseaBusiness & FinanceEquipmentOperations & MaintenanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1WATCH: Second Island Offshore ocean energy construction vessel in Norway for completion
  2. 2United Oil & Gas eyes billion-barrel Jamaican drilling targets as it maps out next steps
  3. 3Folegandros island joins Greece’s mainland power grid via 60-kilometer subsea cable
  4. 4UK’s first HVDC subsea cable factory opens in Scotland

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free