Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Wind Farms›Ørsted Wraps Up Hornsea One Divestment
Wind Farms

November 27, 2018 · about 7 years ago

Ørsted Wraps Up Hornsea One Divestment

Ørsted has completed the divestment of 50% of the Hornsea Project One offshore wind farm in the UK to Global Infrastructure Partners (GIP).

2 minutes read
  • LinkedIn
  • X
  • Email

Ørsted has completed the divestment of 50% of the Hornsea Project One offshore wind farm in the UK to Global Infrastructure Partners (GIP).

Ørsted signed an agreement in September to sell half of the 1.2GW project, under which it will construct the wind farm under a full-scope EPC contract, provide long-term O&M services and provide a route to market for the generated power.

The total sales price includes the acquisition price and the commitment to fund half of the payments under the EPC contract for the complete project, including the transmission assets. It amounts to circa GBP 4.46 billion, due to be paid until 2020.

GIP will partially finance the buy via a multi-tranche financing package equaling more than GBP 3.5 billion, which contains a mixture of investment grade-rated project bonds issued to a consortium of blue-chip institutional debt investors with UK presence, commercial bank loans and mezzanine debt provided by the Danish pension fund PFA, with some tranches guaranteed by Denmark’s Export Credit Agency, EKF.

Located some 120km off the Yorkshire coast, Hornsea Project One will feature 174 Siemens Gamesa 7MW turbines connected to three offshore substations and the world’s first reactive compensation substation (RCS).

The 1.2GW project is scheduled to be fully operational in 2020 when it will become the largest offshore wind farm in the world.

According to information from 1 November , 104 out of 174 turbine monopile foundations and 66 out of 174 inter-array cables have been installed.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Wind FarmsBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1$50 billion South Korean investment pushes stalled Alaska LNG project closer to construction
  2. 2TGS on 3D imaging mission to unlock new insights into Malaysia's offshore discovery
  3. 3Petrobras strikes another oil-bearing zone in Equatorial Margin frontier
  4. 4MidOcean gets hold of $4 billion in major capital raise to fuel global LNG push

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free