Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Contract Awarded for New Dragline Machine
Dredging

August 27, 2019 · about 7 years ago

Contract Awarded for New Dragline Machine

The U.S. Army Corps of Engineers, Memphis District recently awarded a $15 million contract to construct a new dragline machine to Seatrax, Inc., of Houston, Texas. Procurement of this new machine represents Phase I of a project to replace the current dragline machine. Workers will eventually mount t

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Memphis District recently awarded a $15 million contract to construct a new dragline machine to Seatrax, Inc., of Houston, Texas.

Procurement of this new machine represents Phase I of a project to replace the current dragline machine.

Workers will eventually mount the machine on a barge, allowing it to work from the river. A separate contract for the barge is set to open bids on Sept. 11, 2019.

The dragline machine is an integral part of the Memphis District Bank Grading Unit (BGU) operation. The BGU works in tandem with the Clearing and Snagging Unit (CSU), which first removes vegetation and other material from the riverbank.

Then, the BGU steps in using the dragline machine and a fleet of bulldozers to smooth the river bank to a specific grade or angle. The work of the BGU and CSU prepare the riverbank for the Vicksburg District to, next, lay articulate concrete mattress to protect and stabilize the riverbank.

Protection and stabilization of the riverbanks are important to the flood control and navigation components of the Mississippi River and Tributaries Project.

Construction of the current dragline machine began in 1949 and it entered service around 1951. The massive bucket on the end of the dragline can hold 15 cubic yards of soil and silt, and can move an average of 10,000 cubic yards of this material each workday.

“ We expect the new machine to be capable of moving 20,000 cubic yards per workday, doubling the current production rate ,” said Jake Storz, project manager for the BGU replacement contracts .

Storz added that the goal is to have the new dragline machine in service in fiscal year 2022.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Baker Hughes helping chart a course for LNG and monetize Venezuela’s gas reserves
  2. 2Yinson Production and Eni amplifying African FPSO’s gas capacity
  3. 3Sea Lion project on the hunt for new contractors amid Argentine sanction threats
  4. 4Seatrium picks up 9th FSRU conversion job with Karpowership

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free