Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›GLDD to Begin Kings Bay Entrance Channel Dredging Work
Dredging

December 4, 2019 · about 6 years ago

GLDD to Begin Kings Bay Entrance Channel Dredging Work

The U.S. Army Corps of Engineers, Jacksonville District, will begin operations and maintenance dredging of the Kings Bay Entrance Channel and sections of the inner channel this month. USACE awarded a $15.5 million contract in September to the Great Lakes Dredge & Dock Company, LLC, to execute the pr

2 minutes read
  • LinkedIn
  • X
  • Email

The U.S. Army Corps of Engineers, Jacksonville District, will begin operations and maintenance dredging of the Kings Bay Entrance Channel and sections of the inner channel this month.

USACE awarded a $15.5 million contract in September to the Great Lakes Dredge & Dock Company, LLC, to execute the project.

According to the Corps, Great Lakes plans to begin equipment mobilization during the second week of December, which will include staging of piping on the beaches. Dredging operations will commence early January 2020.

“ This project is vital for ensuring mission critical navigation for Naval Submarine Base Kings Bay, the East coast home to the Ohio Class submarines ,” said Project Manager Beau Corbett .

The project will include the beneficial placement of an estimated 300,000 cubic yards of beach compatible sand on northern portions of Fernandina Beach.

The Corps estimates the contractor will also disperse some 900,000 cubic yards of non-beach compatible sand in both an approved near-shore disposal area and an offshore disposal site.

The planned beach fill area will extend from the Fort Clinch Area Boundary (1700 North Fletcher) to Main Beach. The Dolphin Avenue parking lot will serve as a staging area, with safety fencing provided as required, throughout the period of operations.

The contract calls for hopper dredging operations to be completed by March 31, 2020, and the entire project, including equipment demobilization and any site restoration work that may be necessary, by April 19, 2020.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & FinanceProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Connecting the offshore energy industry through smarter travel
  2. 2Borr Drilling’s rig trio lines up jobs in Africa and Europe
  3. 3Inpex broadens its Southeast Asian horizons with two offshore blocks
  4. 4Dutch LNG terminal capacity rises to 20 billion cubic meters with 4th tank

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free