Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Following the Completion of Berdyansk Gig Dredger Meotida Returns to Mariupol
Dredging

February 6, 2020 · about 6 years ago

Following the Completion of Berdyansk Gig Dredger Meotida Returns to Mariupol

The Ukrainian Sea Ports Authority (USPA) has just announced that the hopper dredger Meotida of their Delta-pilot branch has successfully completed its work on the section of the Berdyansk seaport approach channel, after which the vessel was relocated to Mariupol. As reported, the dredger Meotida has

1 minutes read
  • LinkedIn
  • X
  • Email
Following the Completion of Berdyansk Gig Dredger Meotida Returns to Mariupol
Image source: USPA

The Ukrainian Sea Ports Authority (USPA) has just announced that the hopper dredger Meotida of their Delta-pilot branch has successfully completed its work on the section of the Berdyansk seaport approach channel, after which the vessel was relocated to Mariupol.

As reported, the dredger Meotida has been operating in Berdyansk since early August 2019. During this period, the vessel managed to remove nearly 300,000 cubic meters of dredge spoil.

In Mariupol, dredging will primarily be performed on the 9-11th kilometer section of the coal harbor approach channel.

At the same time, the implementation of a large-scale dredging project in the Berdyansk port continues. The work is being performed by the dredging contractor “Azimut” Specialized Technical Bureau” LLC with the help of “DUNAY” multi-bucket dredger, three scows and the “UMD HERCULES” hopper dredger.

The total amount of work to be performed by the contractor in the Berdyansk port is 1,850,000 cubic meters, currently the project is almost 40 percent complete.

Recall that from 29 January 2020, the Berdyansk seaport increased the canal draught for vessels on the approach channel to 7.8m. The overall goal is to increase the canal draught in the Berdyansk port to the passport indicators – 7.9m.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1$50 billion South Korean investment pushes stalled Alaska LNG project closer to construction
  2. 2TGS on 3D imaging mission to unlock new insights into Malaysia's offshore discovery
  3. 3Petrobras strikes another oil-bearing zone in Equatorial Margin frontier
  4. 4MidOcean gets hold of $4 billion in major capital raise to fuel global LNG push

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free