Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Dredging›Block Island Dredging Proposed
Dredging

April 8, 2020 · about 6 years ago

Block Island Dredging Proposed

The U.S. Army Corps of Engineers, New England District, is proposing maintenance dredging of the Block Island Harbor of Refuge Federal Navigation Project (FNP) on Block Island, Rhode Island. The Town of New Shoreham is the sponsor and requested that this project be maintained, said USACE. The propos

2 minutes read
  • LinkedIn
  • X
  • Email
Block Island Dredging Proposed
Image source: USACE

The U.S. Army Corps of Engineers, New England District, is proposing maintenance dredging of the Block Island Harbor of Refuge Federal Navigation Project (FNP) on Block Island, Rhode Island.

The Town of New Shoreham is the sponsor and requested that this project be maintained, said USACE.

The proposed work involves maintenance dredging of portions of the 15-foot-deep Mean Lower Low Water (MLLW) inner harbor which is made up of an anchorage area, inner channel, and inner basin, plus 2 feet authorized overdepth, in the Harbor of Refuge FNP.

No maintenance dredging of the FNP entrance channel will occur as a part of the proposed work. Sediment in the western portion of the 15-foot inner basin has been determined to be unsuitable for open water placement and will not be dredged.

Natural shoaling processes have reduced available depths to as little as 1.0 foot in the 15-foot MLLW anchorage making navigation hazardous at lower stages of the tide. Maintenance dredging of approximately 50,000 cubic yards of silt and fine-grained sand from approximately 6 acres of the authorized project area will restore the inner harbor portion of the FNP to authorized dimensions.

Approximately 32,000 cubic yards of sand material is proposed for placement at the previously-used, nearshore placement site off of Crescent Beach. The remaining silty material (approximately 18,000 cubic yards) will be placed at the Rhode Island Sound Disposal Site (RISDS).

A private contractor, under contract to the government, will use a mechanical dredge and scows to remove the material and then transport it for placement at the disposal sites.

Construction is expected to take between 3-4 months between Oct. 1 and Jan. 31 of the year(s) in which funds become available.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

DredgingBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 122-year Cheniere-Petrobras LNG pact expands energy bridge between North and South America
  2. 2Next chapter of Shell’s Canadian LNG project brings Fluor-JGC JV multibillion-dollar award
  3. 3Subsea production systems for Mozambique’s deepwater LNG project ordered from OneSubsea
  4. 4Shell’s platform departs for Trinidad & Tobago’s offshore realm as NGC locks in gas from two upcoming projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free