Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›Energean Power FPSO hull reaches Singapore but yard operations in two-week halt
Fossil Energy

April 15, 2020 · about 6 years ago

Energean Power FPSO hull reaches Singapore but yard operations in two-week halt

Energean’s FPSO unit, meant for the Karish and Tanin development offshore Israel, has reached Sembcorp Marine’s shipyard in Singapore.

1 minutes read
  • LinkedIn
  • X
  • Email
Energean Power FPSO hull
Energean Power FPSO hull; Source: Energean

Energean’s hull for the Energean Power FPSO, meant for the Karish and Tanin development offshore Israel, has arrived at the Sembcorp Marine’s shipyard in Singapore for topside integration. However, the integration works will not start for at least another two weeks due to a temporary halt of operations at the yard.

The hull started its journey from a COSCO yard in China heading towards Singapore on 3 April 2020.

Energean said on Wednesday that the Energean Power FPSO hull had arrived at the Sembcorp Marine Admiralty Yard in Singapore on 15 April 2020.

While in Singapore, the FPSO topsides will be integrated, before the completed FPSO is towed to the Karish field in Israel for installation and hook-up.

However, upon arrival, Energean was informed of a two-week temporary halt to operations at the yard, starting 17 April 2020, which is intended to reduce the risk of COVID-19 transmission.

Sembcorp Marine will secure the hull mooring during this period.

Energean said in March that good progress had been made on the construction of the topsides in Singapore, and Energean was working with TechnipFMC to mitigate the impact of the deferred sail away from China on Practical Completion of the project.

During 2020, all components of the subsea production system will be installed using vessels provided by TechnipFMC. The first gas on the Karish project is on track for H1 2021.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyFPSO & VesselsOil & GasBusiness Developments & ProjectsExploration & ProductionProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Fugro performs ultra-deepwater AUV survey off East Malaysia
  2. 2Southeast Asian oil field development clears key environmental hurdle to move toward FID
  3. 3‘Major’ oil & gas player awards Shearwater with three-year contract off South America
  4. 4Noble’s 2013-built drillship scoops up 10-well job in Africa with Tullow Oil

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free