Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Foundations›Lamprell and ScottishPower settle East Anglia 1 tab
Foundations

April 23, 2020 · about 6 years ago

Lamprell and ScottishPower settle East Anglia 1 tab

Lamprell and ScottishPower Renewables have reached a final settlement with regards to the close-out of the East Anglia One project. The final settlement will result in a cash payment to Lamprell of USD 18.9 million in May 2020, the UAE-based offshore engineering and fabrication company said. In addi

2 minutes read
  • LinkedIn
  • X
  • Email
Lamprell and ScottishPower settle East Anglia 1 tab
Lamprell

Lamprell and ScottishPower Renewables have reached a final settlement with regards to the close-out of the East Anglia One project.

The final settlement will result in a cash payment to Lamprell of USD 18.9 million in May 2020, the UAE-based offshore engineering and fabrication company said.

In addition, Lamprell will now commence the process of releasing up to USD 23 million of the USD 35 million in restricted cash relating to the project performance guarantee, approximately half of which is expected to be released in the coming months.

This settlement removes both the risk of liquidated damages of USD 33.8 million and will materially improve Lamprell’s liquidity by approximately USD 40 million in due course as set out below, the company said.

In September 2019, Lamprell reported project losses of USD 95.6 million up to the period ended 30 June 2019.

Following this final settlement and subject to audit, the overall project losses amount to USD 118.2 million, an additional loss of USD 22.6 million that will materially affect the company’s financial performance for the year ended 31 December 2019, the company said.

The project loss covers all outstanding works to completion and the increased costs incurred by the subcontractor, Harland and Wolff, in Belfast. Lamprell now anticipates that, subject to audit, 2019 revenue to be slightly lower than previous guidance at USD 260 million.

The 714MW East Anglia One project comprises 102 Siemens 7MW turbines located 59 kilometres from the coast of Lowestoft, the UK. the wind farm is scheduled to be fully operational this year.

In November 2016, ScottishPower Renewables awarded Lamprell with a USD 225 million contract to manufacture and deliver 60 out of the 102 jacket foundations and the accompanying piles for the project.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

FoundationsOffshore WindBusiness & Finance

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1North Sea appraisal ops up the oil & gas discoveries’ projected size
  2. 2Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  3. 3CNOOC keeping Worley busy on its North Sea assets for five more years
  4. 4Fit-out of NeuConnect’s converter stations in progress

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free