Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Fossil Energy›BW Energy sees delay in Gabon well hook-up
Fossil Energy

May 4, 2020 · about 6 years ago

BW Energy sees delay in Gabon well hook-up

BW Energy has experienced a delay in hook-up operations of a well in the Dussafu Marin Permit, offshore Gabon, due to the coronavirus crisis.

2 minutes read
  • LinkedIn
  • X
  • Email
FPSO BW Adolo
FPSO BW Adolo; Sorce: BW Offshore

BW Energy has experienced a delay in hook-up operations for a well in the Dussafu Marin Permit, offshore Gabon, due to the coronavirus crisis.

There are five oil fields within the Dussafu Permit: Moubenga, Walt Whitman, Ruche, Ruche North East, and Tortue.

Two months after the production start-up at the Tortue Phase 1, BW in November 2018 sanctioned the second phase of its Tortue development.

Phase 2 development activities started in 2019 and continued into 2020. This phase consists of four production wells, tied back to the FPSO BW Adolo.

The DTM-4H and DTM-5H were the first of two clusters. The second cluster was scheduled to begin production by June 2020.

Covid-19 restrictions

However, Panoro, a partner in the project, informed on Monday that the hook-up was delayed due to the coronavirus pandemic.

Panoro said that the production in Gabon for 2020 is now expected to average 15,000-16,500 bopd (gross), with the 10 per cent reduction in range due to the uncertain timing of hooking up the completed DTM-6 well.

The well was expected to be connected in June but, given the COVID-19 restrictions, the timing of this activity is estimated to occur later this year.

The Tortue development will upon completion of Phase 2 have six wells. Total production after the completion of Phase 2 is projected to be 17.3 – 21.6 kbopd gross for 2020 from six producing wells, compared with an average of 11.8 kbopd gross produced in 2019.

Current production is approximately 17,500 bopd (gross), with operating costs decreased from 2019 levels to $16-18 per barrel.

Panoro also said that lifting was completed in March for the account of Panoro, BW, and Tullow, followed by lifting in April on behalf of the State of Gabon.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Fossil EnergyFPSO & VesselsOil & GasBusiness & FinanceBusiness Developments & ProjectsExploration & ProductionProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Fugro performs ultra-deepwater AUV survey off East Malaysia
  2. 2Southeast Asian oil field development clears key environmental hurdle to move toward FID
  3. 3‘Major’ oil & gas player awards Shearwater with three-year contract off South America
  4. 4Noble’s 2013-built drillship scoops up 10-well job in Africa with Tullow Oil

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free