Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Living Stone completes cable burial at SeaMade offshore wind farm
Cabling

June 30, 2020 · about 6 years ago

Living Stone completes cable burial at SeaMade offshore wind farm

DEME’s cable laying vessel Living Stone has completed the cable burial activities at the SeaMade offshore wind farm site in the Belgian sector of the North Sea. The vessel started the inter-array cable laying works in April and connected the first cables to one of the project’s offshore substations

1 minutes read
  • LinkedIn
  • X
  • Email
The Living Stone vessel sailing at the cable burial area at SeaMade site
SeaMade NV

DEME’s cable laying vessel Living Stone has completed the cable burial activities at the SeaMade offshore wind farm site in the Belgian sector of the North Sea.

The vessel started the inter-array cable laying works in April and connected the first cables to one of the project’s offshore substations (OSS) at the end of the same month.

The cable burial works started in early May.

Living Stone finished installing all 64 inter-array cables with a total length of 71.2 kilometres at the SeaMade site at the end of May.

The vessel completed the export cable installation in December 2019.

The 487 MW SeaMade offshore wind farm consists of the 235 MW Mermaid and the 252 MW Seastar offshore wind projects, and two offshore substations.

All foundations at the project site have been in place since the beginning of January.

The installation of 58 Siemens Gamesa 8.4 MW turbines started in the second half of June, with the first wind turbine erected a few of days later.

SeaMade is scheduled to be operational by the end of the year.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingOffshore WindSubseaWind FarmsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free