Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Foundations›Sea & Land Project Engineering secures Hollandse Kust Noord deal
Foundations

July 7, 2020 · about 6 years ago

Sea & Land Project Engineering secures Hollandse Kust Noord deal

Sea & Land Project Engineering has been appointed to provide the detailed design of the offshore transformer station jacket and foundations for the Hollandse Kust Noord offshore wind farm. The offshore transformer station consists of a 45m jacket weighing 1,930t and 870t piles supporting a topside s

1 minutes read
  • LinkedIn
  • X
  • Email
Sea-Land-Project-Engineering-Secures-Hollandse-Kust-Noord-Deal
TenneT

Sea & Land Project Engineering has been appointed to provide the detailed design of the offshore transformer station jacket and foundations for the Hollandse Kust Noord offshore wind farm.

The offshore transformer station consists of a 45m jacket weighing 1,930t and 870t piles supporting a topside structure consisting of four decks weighing approximately 4,100t, the company said.

Recently, TenneT selected the consortium of ENGIE Fabricom and Iemants to design, engineer, produce, deliver, transport, and install the 700 MW offshore substation for Hollandse Kust Noord.

Engineering activities have commenced and construction work for the topside and jacket will start in October.

The load-out of the jacket is planned for Q3 2021. The topside is scheduled to leave ENGIE’s yard in Hoboken in the spring of 2022.

The Hollandse Kust Noord wind farm will comprise two zones with a combined capacity of between 693 MW and 760 MW.

The zero-subsidy tender round for the rights to build and operate the wind farm closed on 30 April. RVO plans to announce the winner by the end of July.

The wind farm is expected to be operational by 2023.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

FoundationsOffshore WindProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1North Sea appraisal ops up the oil & gas discoveries’ projected size
  2. 2Vantris Energy rakes in $441.8 million for Petronas and PTTEP offshore works in Malaysia
  3. 3CNOOC keeping Worley busy on its North Sea assets for five more years
  4. 4Fit-out of NeuConnect’s converter stations in progress

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free