Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Grid›Jacket for second Moray East OTM in place
Grid

August 14, 2020 · about 6 years ago

Jacket for second Moray East OTM in place

The jacket foundation for the second of the three Moray East’s Offshore Transformer Modules (OTMs) was installed on 10 August, according to the project’s Notice of Operations. Siemens Energy shipped out the first OTM, ME OSP2, on 30 June. However, this was not the first OTM to have been installed. A

1 minutes read
  • LinkedIn
  • X
  • Email
Moray East OTM OSP2
Smulders

The jacket foundation for the second of the three Moray East’s Offshore Transformer Modules (OTMs) was installed on 10 August, according to the project’s Notice of Operations.

Siemens Energy shipped out the first OTM, ME OSP2, on 30 June. However, this was not the first OTM to have been installed.

As reported a few days ago, the first of the three OTMs to be put in place was ME OSP3, shortly after it was dispatched from Belgium, where Smulders and Engie Fabricom are building the OTMs for Siemens Energy, which secured the contract to connect the wind farm to the grid in 2018.

A DEME spokesperson said that the OSP2 would be installed later this week.

Moray East will comprise 100 MHI Vestas 9.5 MW wind turbines expected to be operational by 2022.

The OTMs will transform the output of the offshore wind farm’s wind turbines from 66 kilovolts (kV) to the transmission voltage of 220kV.

Other grid connection works are also under way at the project site off Scotland, with the first export power cable now installed. The cable, installed by NKT, made landfall at Inverboyndie.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

GridOffshore WindBusiness Developments & ProjectsInfrastructure

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free