Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Deepwater Installation›Jacket foundation for Moray East OSP1 in place
Deepwater Installation

August 31, 2020 · about 6 years ago

Jacket foundation for Moray East OSP1 in place

The jacket foundation for the third offshore transformer module (OTM) for Moray East offshore wind farm has been installed at the site off the Scottish coast. According to the project’s latest Notice of Operations, the jack-up vessel Seajacks Scylla installed the OSP1 jacket on 30 August. Meanwhile,

1 minutes read
  • LinkedIn
  • X
  • Email
An archive photo of Seajacks Scylla, the vessel now installing jacket foundations at the Moray East offshore wind farm
Seajacks (archive)

The jacket foundation for the third offshore transformer module (OTM) for Moray East offshore wind farm has been installed at the site off the Scottish coast.

According to the project’s latest Notice of Operations, the jack-up vessel Seajacks Scylla installed the OSP1 jacket on 30 August. Meanwhile, the OSP1 topside was scheduled to sail out from Belgium during the weekend.

The first OTM (OSP3) was installed on 10 August, when the jacket foundation for OSP2 was also put in place. The OSP2 topside, which was shipped out from Belgium on 30 June, was installed shortly after its jacket.

The OTMs, for which Siemens Energy secured a contract in 2018, were fabricated by Smulders and ENGIE Solutions in Hoboken, Belgium.

The platforms will be linked together to cover Moray East’s rated capacity of 950 MW and will transform the output of the wind turbines from 66 kV to the transmission voltage of 220 kV, and transmit the electricity to the grid on land.

Moray East, comprising 100 MHI Vestas 9.5 MW wind turbines, is scheduled for full commissioning in 2022.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Deepwater InstallationFoundationsGridOffshore WindSubseaProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free