Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Foundations›28 jackets to go at Moray East
Foundations

November 24, 2020 · about 5 years ago

28 jackets to go at Moray East

Seajacks Scylla has 28 jacket foundations to install at the Moray East offshore wind farm, before it wraps up one of the biggest offshore construction works on the project. Only this month (November 2020), the vessel has put in place 18 jackets, so the foundation installation is expected to be compl

1 minutes read
  • LinkedIn
  • X
  • Email
A yellow Moray East jacket foundation installed earlier
Moray Offshore Wind Farm (East) Ltd

Seajacks Scylla has 28 jacket foundations to install at the Moray East offshore wind farm, before it wraps up one of the biggest offshore construction works on the project.

Only this month (November 2020), the vessel has put in place 18 jackets, so the foundation installation is expected to be completed in January, at the latest.

The first jacket was installed at the beginning of July, and the quarter of all the project’s foundations were in by the end of August.

The 950 MW wind farm, which will comprise 100 wind turbines and three offshore transformer modules (OTMs), saw all three of its OTMs in place by mid-September.

Smulders has manufactured 55 wind turbine jacket foundations for the project, while Lamprell delivered the remaining 45 and the three jackets for the project’s OTMs.

The Moray East wind turbines will be supplied by MHI Vestas, while the OTMs have been delivered by Siemens Energy.

DEME is the EPCI contractor for Moray East’s foundations and the transport and installation of the OTMs.

The company is using Seajacks Scylla after its newbuild installation vessel Orion went through a crane accident in May, which damaged the crane and the vessel deck.

The 950 MW offshore wind farm, being built some 22 kilometres off the Aberdeenshire coast, is scheduled to be fully operational in 2022.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

FoundationsOffshore WindWind FarmsBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free