All Windpark Fryslân array cables in place

The installation of inter-array cables has been completed at the Windpark Fryslân nearshore wind farm in the IJsselmeer Lake in the Netherlands. The inter-array cables will undergo tests in the coming days, Windpark Fryslân said. The cables connect the wind farm’s 89 Siemens Gamesa 4.3 MW wind turbi

1 minutes read
Windpark Fryslân
Windpark Fryslân

The installation of inter-array cables has been completed at the Windpark Fryslân nearshore wind farm in the IJsselmeer Lake in the Netherlands.

The inter-array cables will undergo tests in the coming days, Windpark Fryslân said.

The cables connect the wind farm’s 89 Siemens Gamesa 4.3 MW wind turbines with the wind farm’s own transformer station at Breezanddijk on the artificial island of Breezand.

From there, two cable circuits which run to Bolsward deliver the electricity generated at the wind farm to TenneT’s Frisian high-voltage grid.

Located some six kilometres off the Frisian coast, the 382.7 MW Windpark Fryslân is the largest wind farm built in a body of fresh water.

The wind farm is being constructed by the Zuiderzeewind consortium of Van Oord and Siemens Gamesa on behalf of Ventolines.

Turbine installation is currently ongoing and the wind farm is expected to be completed by the summer of 2021.

Ventolines is responsible for the project management of Windpark Fryslân during construction and operations.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.