Blue X installation about to begin

Leask Marine is about to begin the installation of the mooring system and Blue X device at the European Marine Energy Center (EMEC) nursery site in Scapa Flow.

1 minutes read
Photo showing Mocean Energy’s Blue X device in Orkney (Courtesy of EMEC/Photo by Colin Keldie)
Mocean Energy’s Blue X device in Orkney (Courtesy of EMEC/Photo by Colin Keldie)

Leask Marine is about to begin the installation of the mooring system and Blue X device at the European Marine Energy Center (EMEC) nursery site in Scapa Flow.

The company will be installing the wave energy converter between 8 June and 30 June 2021.

After the initial trials set to take place at Scapa Flow test site, the Blue X prototype will be deployed at the centre’s large scale Billia Croo test site in summer 2021.

Next year, Mocean Energy plans to connect the device to a subsea battery which will be used to power a remotely operated autonomous underwater vehicle (AUV).

In April, Mocean Energy revealed the Blue X wave power prototype, a 20-metre long, 38-tonne machine manufactured in Scotland.

At the end of April, the company concluded wet commissioning and two weeks later, Blue X arrived at Hatston Pier, Kirkwall in Orkney.

Advertisement

EMEC recently opened up a consultation on the decommissioning programme for stakeholders and the public to submit their responses and possible concerns.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.