Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Baltic Pipe construction at full throttle with 50km done
Cabling

July 8, 2021 · about 5 years ago

Baltic Pipe construction at full throttle with 50km done

Saipem’s pipelay vessel Castorone has installed 50 kilometers of the gas pipeline for the Baltic Pipe project in the Baltic Sea. Approximately 225 kilometers remain to be laid by Saipem’s pipelay trio of Castorone, Castoro Sei and Castoro 10, project developers reported. Castorone began laying the o

1 minutes read
  • LinkedIn
  • X
  • Email
Baltic Pipe construction at full throttle with 50km done
Credits to GAZ-SYSTEM

Saipem’s pipelay vessel Castorone has installed 50 kilometers of the gas pipeline for the Baltic Pipe project in the Baltic Sea.

Approximately 225 kilometers remain to be laid by Saipem’s pipelay trio of Castorone, Castoro Sei and Castoro 10, project developers reported.

Castorone began laying the offshore gas pipeline at the end of June at a site close to the island of Bornholm, Denmark.

Baltic Pipe will create a new corridor supplying gas from Norway to the markets in Poland, Denmark and also neighboring countries.

The project recently faced a setback as the Danish Environmental and Food Appeals Board ruled to repeal the permit for the onshore part of Baltic Pipe in early June, stating that the environmental assessment does not sufficiently describe the measures taken to protect certain animal species.

Energinet and the Danish Environmental Protection Agency now need to make a new environmental impact assessment for the project, which could take up to 8 months of work.

However, shortly after the permit repeal, Danes allowed construction works to resume in certain parts of the project across Denmark.

Related Articles

Cabling

Baltic Pipe needs new environmental permit, process could take up to 8 months

2 min read

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingFossil EnergyOil & GasSubseaBusiness Developments & ProjectsProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free