Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Second subsea cable batch on its way to 310 MW Vietnamese OWF
Cabling

August 24, 2021 · about 5 years ago

Second subsea cable batch on its way to 310 MW Vietnamese OWF

China-based power cable company Orient Cable has shipped the second batch of subsea cables for the Binh Dai offshore wind project in Vietnam.

1 minutes read
  • LinkedIn
  • X
  • Email
Second subsea cable batch on its way to 310 MW Vietnamese OWF
Courtesy of Orient Cable

China-based power cable company Orient Cable has shipped the second batch of subsea cables for the Binh Dai offshore wind project in Vietnam .

According to the company’s update, subsea cables together with 150 pieces of accessories, including hang-off, cable protection system (CPS) and termination, are on the way to Vietnam.

They will be installed in the BinhDai District in a very short time and come into operation this year, Orient Cable said.

To remind, the company secured the EPCI contract for the wind farm in September 2020 to provide and install 185 kilometres of the 35 kV subsea cable system.

Orient Cable delivered the first shipment of cables in March this year and started the first subsea cable laying work at the Vietnamese offshore wind project in June.

Related Articles

Cabling

Cable laying begins at Vietnam’s Binh Dai wind farm

2 min read

Binh Dai is located seven kilometres offshore and due to the proximity to the mainland it will use 35kV submarine cable to connect the offshore turbines to the onshore substation directly.

Mekong Wind Power Joint Stock Company is developing the 310 MW wind farm which will comprise 74 turbines, Siemens Gamesa 4.5 MW and Goldwind 3.3 MW units, to be installed in phases.

The consortium of PowerChina Huadong Engineering Corporation and PowerChina International Group is the EPC contractor for the project.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingOffshore WindSubseaWind FarmsBusiness Developments & Projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 122-year Cheniere-Petrobras LNG pact expands energy bridge between North and South America
  2. 2Next chapter of Shell’s Canadian LNG project brings Fluor-JGC JV multibillion-dollar award
  3. 3Subsea production systems for Mozambique’s deepwater LNG project ordered from OneSubsea
  4. 4Shell’s platform departs for Trinidad & Tobago’s offshore realm as NGC locks in gas from two upcoming projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free