Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Offshore Wind›America’s first large-scale offshore wind farm reaches financial close
Offshore Wind

September 16, 2021 · about 5 years ago

America’s first large-scale offshore wind farm reaches financial close

Vineyard Wind, a joint venture between Avangrid Renewables and Copenhagen Infrastructure Partners (CIP), has reached financial close on its 800 MW offshore wind farm in Massachusetts — the first large-scale offshore wind farm in the United States and the Americas region. The developer has raised $ 2

2 minutes read
  • LinkedIn
  • X
  • Email
A photo of an offshore wind farm for illustration
Vineyard Wind/Illustration

Vineyard Wind, a joint venture between Avangrid Renewables and Copenhagen Infrastructure Partners (CIP), has reached financial close on its 800 MW offshore wind farm in Massachusetts — the first large-scale offshore wind farm in the United States and the Americas region.

The developer has raised $ 2.3 billion of senior debt through nine international and U.S. banks to finance the construction of the project, which now enables Vineyard Wind to give the go-ahead to its contractors.

At $ 2.3 billion, Vineyard Wind 1 represents one of the largest investments in a single renewable energy projects in the U.S.

Vineyard Wind 1 is also the first commercial scale offshore wind farm in the U.S. to achieve financial close, which comes a few months after the project was approved by the government and received the U.S. Environmental Protection Agency’s (EPA) final Clean Air Act Outer Continental Shelf air quality permit .

Related Articles

Business Developments & Projects

U.S. approves first large-scale offshore wind project

3 min read

Construction works will first start onshore in Barnstable, where the offshore wind farm will connect to the national grid on land. Onshore works are scheduled to begin this Fall.

Offshore work will commence in 2022 with the installation of foundations and cables, followed by wind turbines.

The 800 MW project will feature next-generation GE Haliade-X wind turbines, to be installed by DEME Offshore’s U.S. arm. The monopiles and transition pieces, which will be delivered by Sif and Windar , will be installed by Heerema Marine Contractors .

Jan De Nul will install inter-array cables supplied by JDR, while the export cables will be delivered by Prysmian .

The 800 MW Vineyard Wind 1 is scheduled to deliver its first power to the grid in 2023.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

Offshore WindWind FarmsBusiness & FinanceBusiness Developments & Projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free