Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Date set for Baltic Pipe opening ceremony
Cabling

August 5, 2022 · about 4 years ago

Date set for Baltic Pipe opening ceremony

Polish gas transmission system operator GAZ-SYSTEM will hold the opening ceremony for the Baltic Pipe project on 27 September. The announcement comes as the technical commissioning of all three gas compressor stations that will distribute gas imported from the Norwegian Shelf in Poland has been comp

2 minutes read
  • LinkedIn
  • X
  • Email
Date set for Baltic Pipe opening ceremony
Courtesy of Baltic Pipe

Polish gas transmission system operator GAZ-SYSTEM will hold the opening ceremony for the Baltic Pipe project on 27 September.

The announcement comes as the technical commissioning of all three gas compressor stations that will distribute gas imported from the Norwegian Shelf in Poland has been completed.

Technical readiness was first confirmed for the gas compressor station in Odolanów, which is the largest one, followed by the one in Goleniów and then in Gustorzyn.

According to GAZ-SYSTEM, all three are currently in the process of gassing and finishing works.

“Thanks to the expansion of the two existing compressor stations and the construction of a new one in Gustorzyn, the total gas compression capacity in the national transmission system will increase by over 50%, which will significantly improve the flexibility and security of the transmission network,” said Tomasz Stępień , president of GAZ-SYSTEM.

Related Articles

Subsea

Baltic Pipe is now connected to Polish and Danish transmission systems

2 min read

The technical commissioning was divided into two stages in order to maintain the smooth operation of the works, the company said.

The capacity of the Odolanów gas compressor station will increase by 30 MW, and the capacity will be from 280,000m 3 /h to 1,380,000m 3 /h of gas, while the capacity of the Goleniów compressor station will increase by 25 MW after the expansion.

The third gas compressor station, built from scratch in Gustorzyna, was equipped with three compressor units with a total capacity of 20 MW.

Baltic Pipe is said to be one of the largest infrastructure investments in Poland and has been awarded the “Project of Common Interest” status by the European Commission.

The 274-kilometer link is scheduled for partial commissioning this October and full commissioning on 1 January 2023, at a full annual capacity of up to 10 BCM.

Register for Offshore Energy Exhibition & Conference:

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingDeepwater InstallationFossil EnergySubseaBusiness & FinanceBusiness Developments & ProjectsInfrastructureProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free