Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›Technical challenges postpone launch of Baltic Pipe receiving terminal
Cabling

October 7, 2022 · about 4 years ago

Technical challenges postpone launch of Baltic Pipe receiving terminal

Commissioning of Baltic Pipe’s receiving terminal in Western Jutland is set to be further delayed due to technical challenges. This, however, will have no impact on the gas volumes sent to Poland. The receiving terminal for gas from Norway’s Europipe II should have been commissioned this Saturday, 8

2 minutes read
  • LinkedIn
  • X
  • Email
Technical challenges postpone launch of Baltic Pipe receiving terminal
GAZ-SYSTEM

Commissioning of Baltic Pipe’s receiving terminal in Western Jutland is set to be further delayed due to technical challenges. This, however, will have no impact on the gas volumes sent to Poland.

The receiving terminal for gas from Norway’s Europipe II should have been commissioned this Saturday, 8 October, but has been postponed to 20 October.

Energinet stated that the delay is due to challenges with the control systems, among other things.

“The technical challenges on the complex plant are so challenging that we cannot go into operation in Nybro as planned. We notified the gas market of this today, Friday. We are working hard to solve the problems, and fortunately we have good cooperation with our contractors on site,” said Torben Brabo , Energinet’s director of international relations.

The delay means that gas from Europipe II cannot flow into Baltic Pipe via Nybro until 20 October. This will not affect the volume of gas to Poland.

Related Articles

Cabling

Baltic Pipe launches, full start-up expected one month earlier

2 min read

To remind, Baltic Pipe was commissioned with partial capacity on 1 October. The volume of gas to Poland will be continuously increased until full commissioning at the end of November.

As previously announced, commissioning at full capacity, up to 10 billion cubic meters of gas per year, can take place before originally planned because the work of laying the last pipelines in the ground in East Jutland and in West Funen has progressed faster than expected.

The last weld on the underground gas pipeline section was carried out this week, Energinet added.

Related Articles

Cabling

First gas flows between Denmark and Norway after Baltic Pipe North Sea construction ends

2 min read

Subscribe

Offshore Energy daily newsletter

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingFossil EnergyOil & GasSubseaBusiness & FinanceBusiness Developments & ProjectsInfrastructureProject & Tenders

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Digital twin technology to help improve safety of ammonia-fueled vessels
  2. 2Serica’s UK gas footprint widens as it brings Spirit Energy's North Sea assets into its fold
  3. 3Boskalis to install inter-array cables at 1 GW Dutch offshore wind farm
  4. 4Norway's CO2 transport and storage project gets second Swedish customer

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free