Offshore Energy
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
  • More news
JobsNewsletter
Offshore Energy logo

Your trusted source for global offshore energy news, part of the Navingo network.

Topics
  • Fossil Energy
  • Subsea
  • Alternative Fuels
  • Hydrogen
  • Marine Energy
Network
  • Offshore Energy
  • Offshore Wind
  • NavalToday
  • Dredging Today
Company
  • Advertising
  • Newsletter
  • Jobs
  • Report your news
  • Privacy

© 2026 Navingo. All rights reserved.

Home›Cabling›All export cables in place at Changfang & Xidao offshore wind farm
Cabling

June 19, 2023 · about 3 years ago

All export cables in place at Changfang & Xidao offshore wind farm

The installation of offshore export cables that will connect Changfang and Xidao offshore wind farms in Taiwan to the grid on land has been completed. Seaway7, which chartered the Topaz Installer vessel for the work, has installed seven export cables totalling 210 kilometres in length, according to

2 minutes read
  • LinkedIn
  • X
  • Email
A photo of CLV Topaz Installer at Changfang & Xidao offshore wind project site
Seaway7 via LinkedIn

The installation of offshore export cables that will connect Changfang and Xidao offshore wind farms in Taiwan to the grid on land has been completed.

Seaway7, which chartered the Topaz Installer vessel for the work, has installed seven export cables totalling 210 kilometres in length, according to the company’s update on social media .

The installation of inter-array cables on the 589 MW offshore wind project, also carried out by Seaway7, started last month. For the cable connections between the turbines, the company has deployed its cable-laying vessel Seaway Phoenix , which will lay approximately 73 kilometres of 66kV inter-array cables.

Related Articles

Cabling

Seaway 7 starts installing Changfang & Xidao inter-array cables

1 min read

In May, the work on installing the pin piles for the wind farm’s jacket foundation was completed, with 50 jacket foundations left to be installed at that time.

The transportation and installation of Changfang and Xidao’s 62 jacket foundations and the 186 accompanying pin piles are being done by Boskalis, which is carrying out the work in a joint venture with Taiwan’s Hwa Chi Construction Co.

The 589 MW Changfang and Xidao offshore wind project will comprise 62 Vestas V174-9.5 MW wind turbines.

Offshore construction at the project’s two sites started in 2021 and the first wind turbine was installed in July of last year.

Offshore construction is expected to be completed by the end of this year.

The 589 MW project – owned by Copenhagen Infrastructure Partners (CIP), which holds the majority stake, and by two local life insurance companies, Taiwan Life Insurance, and TransGlobe Life Insurance –is scheduled to be commissioned in early 2024.

Reach the Offshore Energy industry in one go!

Offshore Energy is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow Offshore Energy on:

Filed under

CablingGridOffshore WindSubseaWind FarmsBusiness Developments & Projects

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Electrical fault triggers oil output deferral and rig intervention plans at Karoon’s Brazilian field
  2. 2TotalEnergies’ Caspian Sea gas and condensate field expansion is a go
  3. 3TotalEnergies earmarks annual spend of up to $17 billion over next five years
  4. 4Fugro performs ultra-deepwater AUV survey off East Malaysia

Daily Offshore Energy News in Your Mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free